ImprovedQuality
See how your QA register fits together
Every item now opens on one card: where it sits, which ITPs it gets from its type and which were added by hand, and what it holds. The register shows its shape first — systems, lots, equipment — and tells you when items sit inside nothing, so nothing rolls up from them. One press groups them into a system, with the move shown before it is made.
ImprovedQuality
Setting up the QA register, guided
A new register now walks you through three steps: choose what gets inspected, build your structure, raise the ITPs. Adding starts by asking whether it is a system, a lot or equipment, and a + on every row adds under it. Add several makes a dozen pours or a whole line by chainage in one go, or takes rows pasted from Excel, and shows every one before anything is created.
NewQuality
A QA pack for any lot or system, in one download
Every lot, system and item now has a QA pack button: a ZIP holding a work-pack index and every ITP and ITR raised against it and everything beneath it, each ITR straight after the ITP it came from. Printed ITPs name the ITR under each row it was carried out as. The index states how many allocated records are not in the pack and why, so a partial pack never passes for a complete one.
NewNCRs
An NCR against a lot holds it open
Raise an NCR straight from a lot, system or item and the form already names it. Until the NCR is closed, that node and everything above it read as outstanding, on the tree, in the warning before closing or energising, and on the Quality Dashboard. The Quality Dashboard also adds up lot quantities now, counting only lots someone has conformed: 1,240 of 2,000 m³, one line per unit.
ImprovedQuality Dashboard
The dashboard reads the whole tree
A switchboard's progress now includes the breakers in it, a feeder's includes every tower and footing on it, and a failed ITR or unreleased hold point anywhere below holds every level above it open. Projects with lots and systems get a lens that turns the lifecycle tiles to each in turn, with readiness in its own words: ready to commission, to close or to energise.
NewQuality
The whole job in one QA tree — systems, lots and equipment
The QA register now holds a circuit, a pour and a breaker side by side. A lot carries its quantity and chainage, a system carries its own commissioning ITPs, and each sits inside the next: the transformer on its foundation, the foundation in its yard. The tree shows every row with the progress of everything beneath it and says in words what has failed or has nothing allocated. Closing a lot or energising a system with work still open asks first and records who went ahead.